Header Image

Save

Center Avenue (McDonald) Area Sanitary Sewer Replacement

Community Involved: McDonald Sewer Authority

Project Goal: To measure the cost-effectiveness of separating a combined sewer system by constructing new sanitary sewers and converting the existing sewer to a dedicated storm sewer.

Project Summary: This project involves total separation of storm and sanitary sewers in the Center Avenue sewershed. New sewers and service laterals will be constructed and existing sewers will be purged and converted to storm sewers. One CSO will be eliminated.

Total Cost: $507,355

3 Rivers Wet Weather Grant Award: $260,205

Start Date: Fall 2000

Completion Date: Fall 2002

Final Report 

Lateral observation port CSO discharge to tributary of Chartiers Creek New sewer construction